Original Budget
$1m
Current Cost
$1m
Cost Overrun
9.8%
0m
Schedule
On Time
| Sector | Transport |
| Responsible Entity | Department of Transport and Planning |
| Status | In Progress |
| Original Completion | 30 Sep 2025 |
| Current Completion | 30 Sep 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.