Original Budget
$4m
Current Cost
$4m
Cost Overrun
0%
Schedule
On Time
Sector Justice & Emergency
Responsible Entity Liquor Control Victoria
Status In Progress
Original Completion 31 Jan 2026
Current Completion 31 Jan 2026
Scope Changes 0 recorded
Cost RAG On Track
Time RAG Unknown
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.

View full project detail →