Original TEI
$1.5m
Current TEI
$1.5m
Cost Overrun
$0.0m
0.0%
Schedule Overrun
4.0 months
Original: Jun 2025 → Oct 2025
Cost Status
On Track
Time Status
At Risk
Description

The project will deliver the system to manage finances, budgets, and procurement processes for VicGrid, in line with VicGrid's requirements and in compliance with Whole of Victorian Government information security standards.

Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.