Report Card: [IT] DC Exit Network Establishment – Phase 2 C
Significant Overruns
Original Budget
$2m
Current Cost
$3m
Cost Overrun
40.2%
1m
Schedule
On Time
| Sector | Information Technology |
| Responsible Entity | CenITex |
| Status | In Progress |
| Original Completion | 30 Oct 2025 |
| Current Completion | 30 Oct 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.