Original Budget
$2m
Current Cost
$3m
Cost Overrun
23.3%
1m
Schedule
On Time
| Sector | Information Technology |
| Responsible Entity | Goulburn-Murray Rural Water Corporation |
| Status | Completed |
| Original Completion | 29 Jun 2025 |
| Current Completion | 29 Jun 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.