Original Budget
$1m
Current Cost
$1m
Cost Overrun
0%
Schedule
+3 months
| Sector | Information Technology |
| Responsible Entity | WorkSafe Victoria |
| Status | In Progress |
| Original Completion | 31 Dec 2025 |
| Current Completion | 31 Mar 2026 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | At Risk |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.