Original TEI
$13.7m
Current TEI
$14.0m
Cost Overrun
+$0.3m
+2.1%
Schedule Overrun
6.0 months
Original: Mar 2025 → Sep 2025
Cost Status
At Risk
Time Status
Off Track
Description

This project will focus on remediating critical data and technology components within GWWs customer property and billing systems to meet KPIs, expected service levels, and customer satisfaction objectives

Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.