Report Card: [IT] Securing Connected Learners (SCL) Program – Phase 2 D
Major Overruns
Original Budget
$3m
Current Cost
$6m
Cost Overrun
96.8%
3m
Schedule
+6 months
| Sector | Education & Training |
| Responsible Entity | Department of Education |
| Status | In Progress |
| Original Completion | 30 Jun 2025 |
| Current Completion | 31 Dec 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | At Risk |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.