Original Budget
$3m
Current Cost
$3m
Cost Overrun
0%
Schedule
+4 months
Sector Information Technology
Responsible Entity Melbourne & Olympic Parks
Status In Progress
Original Completion 30 Jun 2025
Current Completion 31 Oct 2025
Scope Changes 0 recorded
Cost RAG At Risk
Time RAG At Risk
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.