Report Card: [IT] Digital Meter Integrated Software Solution (HES/MDMS) A
On Track
Original Budget
$8m
Current Cost
$8m
Cost Overrun
0%
Schedule
+6 months
| Sector | Information Technology |
| Responsible Entity | Yarra Valley Water Corporation |
| Status | In Progress |
| Original Completion | 30 Jun 2025 |
| Current Completion | 31 Dec 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.