Original Budget
$5m
Current Cost
$7m
Cost Overrun
54.1%
2m
Schedule
+4 months
Sector Information Technology
Responsible Entity WorkSafe Victoria
Status In Progress
Original Completion 30 Jun 2025
Current Completion 30 Oct 2025
Scope Changes 0 recorded
Cost RAG Off Track
Time RAG At Risk
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.

View full project detail →