Original TEI
$3.6m
Current TEI
$6.6m
Cost Overrun
+$3.0m
+82.8%
Schedule Overrun
5.0 months
Original: Apr 2025 → Sep 2025
Cost Status
At Risk
Time Status
At Risk
Description

Phase 2 of Acumen will deliver foundation components, including architecture review and data preparation for ingestion and modelling. This will deliver key foundational elements necessary to support future phases.