Report Card: [IT] Automated System Integration of the Victorian Housing … C
Significant Overruns
Original Budget
$2m
Current Cost
$3m
Cost Overrun
50.0%
1m
Schedule
+4 months
| Sector | Information Technology |
| Responsible Entity | Department of Families, Fairness and Housing |
| Status | In Progress |
| Original Completion | 30 Jun 2025 |
| Current Completion | 31 Oct 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | Off Track |
| Time RAG | At Risk |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.