Original Budget
$2m
Current Cost
$3m
Cost Overrun
25.5%
1m
Schedule
+4 months
Sector Education & Training
Responsible Entity Department of Education
Status In Progress
Original Completion 31 Mar 2025
Current Completion 21 Jul 2025
Scope Changes 0 recorded
Cost RAG On Track
Time RAG At Risk
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.