Report Card: [IT] ARC 4.0 (Expansion and Enhancement - Lessons Plans) D
Major Overruns
Original Budget
$1m
Current Cost
$3m
Cost Overrun
141.1%
2m
Schedule
+11 months
| Sector | Education & Training |
| Responsible Entity | Department of Education |
| Status | Completed |
| Original Completion | 26 Jul 2024 |
| Current Completion | 30 Jun 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.