Report Card: [IT] Mental Health and Wellbeing Client Management System I… D
Major Overruns
Original Budget
$40m
Current Cost
$65m
Cost Overrun
60.8%
24m
Schedule
+24 months
| Sector | Health & Human Services |
| Responsible Entity | Department of Health |
| Status | In Progress |
| Original Completion | 30 Jun 2026 |
| Current Completion | 30 Jun 2028 |
| Scope Changes | 0 recorded |
| Cost RAG | Off Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.