Report Card: [IT] Western Health - Mental Health Transition (ICT Infrast… A
On Track
Original Budget
$2m
Current Cost
$2m
Cost Overrun
0%
Schedule
+10 months
| Sector | Health & Human Services |
| Responsible Entity | Western Health |
| Status | In Progress |
| Original Completion | 30 Oct 2024 |
| Current Completion | 29 Aug 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.