Report Card: [IT] Apprentice and Trainee Management Module Implementation C
Significant Overruns
Original Budget
$3m
Current Cost
$5m
Cost Overrun
34.2%
1m
Schedule
+6 months
| Sector | Education & Training |
| Responsible Entity | Bendigo Kangan Institute of TAFE |
| Status | Cancelled |
| Original Completion | 30 Jun 2025 |
| Current Completion | 31 Dec 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | Off Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.