Original Budget
$1m
Current Cost
$3m
Cost Overrun
100.7%
2m
Schedule
+22 months
| Sector | Information Technology |
| Responsible Entity | Barwon Region Water Corporation |
| Status | In Progress |
| Original Completion | 7 Nov 2024 |
| Current Completion | 31 Aug 2026 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.