Original Budget
$7m
Current Cost
$17m
Cost Overrun
155.3%
11m
Schedule
+24 months
| Sector | Transport |
| Responsible Entity | Department of Transport and Planning |
| Status | In Progress |
| Original Completion | 30 Jun 2024 |
| Current Completion | 30 Jun 2026 |
| Scope Changes | 0 recorded |
| Cost RAG | At Risk |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.