[IT] Rostering System Replacement (WMS)
Original TEI
$5.1m
Current TEI
$7.2m
Cost Overrun
+$2.1m
+40.6%
Schedule Overrun
4.0 months
Original: Jun 2025
→ Oct 2025
Cost Status
At Risk
Time Status
At Risk
Description
The project will replace the current end-of-life rostering software with a new workforce management solution, minimising software stability and security risks, and improving efficiency in rostering processes to deliver more impact to our community.
Cost History (TEI over time)
Timeline Drift
No timeline snapshots recorded yet.