Original Budget
$5m
Current Cost
$5m
Cost Overrun
5.0%
0m
Schedule
+4 months
Sector Information Technology
Responsible Entity Melbourne Water
Status In Progress
Original Completion 22 Jun 2026
Current Completion 26 Oct 2026
Scope Changes 0 recorded
Cost RAG Off Track
Time RAG At Risk
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.