Original Budget
$1m
Current Cost
$1m
Cost Overrun
0%
Schedule
+3 months
Sector Justice & Emergency
Responsible Entity Court Services Victoria
Status Completed
Original Completion 31 Mar 2025
Current Completion 30 Jun 2025
Scope Changes 0 recorded
Cost RAG On Track
Time RAG At Risk
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.