Original Budget
$7m
Current Cost
$7m
Cost Overrun
0%
Schedule
+7 months
| Sector | Information Technology |
| Responsible Entity | Box Hill Institute Group |
| Status | In Progress |
| Original Completion | 28 Feb 2025 |
| Current Completion | 30 Sep 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.