Original Budget
$543m
Current Cost
$680m
Cost Overrun
25.3%
137m
Schedule
+6 months
Sector Transport
Responsible Entity Department of Transport and Planning
Status In Progress
Original Completion 30 Jun 2028
Current Completion 31 Dec 2028
Scope Changes 0 recorded
Cost RAG On Track
Time RAG Off Track
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.