Original TEI
$543.0m
Current TEI
$680.4m
Cost Overrun
+$137.4m
+25.3%
Schedule Overrun
6.0 months
Original: Jun 2028 → Dec 2028
Cost Status
On Track
Time Status
Off Track
Description

The future Public Transport Ticketing (PTT) System will deliver modern customer payment features and progressively replace the current myki Ticketing System (myki System)

Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.