Original Budget
$5m
Current Cost
$4m
Cost Overrun
-6.5%
0m
Schedule
On Time
| Sector | Information Technology |
| Responsible Entity | State Revenue Office |
| Status | Completed |
| Original Completion | 30 Jun 2025 |
| Current Completion | 30 Jun 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.