Report Card: [IT] Enterprise Analytics Platform - Phase 2 C
Significant Overruns
Original Budget
$7m
Current Cost
$8m
Cost Overrun
24.1%
2m
Schedule
+14 months
| Sector | Information Technology |
| Responsible Entity | Yarra Valley Water Corporation |
| Status | In Progress |
| Original Completion | 28 Apr 2025 |
| Current Completion | 30 Jun 2026 |
| Scope Changes | 0 recorded |
| Cost RAG | At Risk |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.