Original TEI
$7.5m
Current TEI
$10.4m
Cost Overrun
+$3.0m
+39.4%
Schedule Overrun
12.0 months
Original: Jun 2024 → Jun 2025
Cost Status
At Risk
Time Status
Off Track
Description

To lead the implementation of SAP SuccessFactors (including Payroll) for DTP . Program scope includes the changes required for the Machinery of Government (MoG) changes announced in December 2022.

Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.