Original TEI
$1.8m
Current TEI
$2.4m
Cost Overrun
+$0.6m
+34.8%
Schedule Overrun
8.9 months
Original: Dec 2024 → Sep 2025
Cost Status
On Track
Time Status
Off Track
Description

Due to a vendor decision to move all on-premise customers to SaaS by 2024 this project is required to upgrade Melbourne Waters finance system and move to the cloud.

Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.