Original Budget
$8m
Current Cost
$11m
Cost Overrun
33.4%
3m
Schedule
+4 months
Sector Information Technology
Responsible Entity Essential Services Commission
Status Completed
Original Completion 24 Jan 2025
Current Completion 2 Jun 2025
Scope Changes 0 recorded
Cost RAG On Track
Time RAG At Risk
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.