Report Card: [IT] Business Intelligence & Analytics Replacement System (… A
On Track
Original Budget
$3m
Current Cost
$3m
Cost Overrun
0%
Schedule
+4 months
| Sector | Health & Human Services |
| Responsible Entity | Royal Women’s Hospital |
| Status | Completed |
| Original Completion | 30 Nov 2024 |
| Current Completion | 7 Apr 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | At Risk |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.