Report Card: [IT] Patient Engagement/Entertainment System (PES) B
Minor Issues
Original Budget
$4m
Current Cost
$4m
Cost Overrun
0%
Schedule
+15 months
| Sector | Health & Human Services |
| Responsible Entity | Northern Health |
| Status | In Progress |
| Original Completion | 30 Jul 2024 |
| Current Completion | 31 Oct 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | At Risk |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.