Original Budget
$4m
Current Cost
$4m
Cost Overrun
-2.1%
0m
Schedule
+12 months
| Sector | Information Technology |
| Responsible Entity | WorkSafe Victoria |
| Status | In Progress |
| Original Completion | 30 Jun 2025 |
| Current Completion | 26 Jun 2026 |
| Scope Changes | 0 recorded |
| Cost RAG | Off Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.