Report Card: [IT] Digital Records & Information Management Shared Servic… C
Significant Overruns
Original Budget
$2m
Current Cost
$3m
Cost Overrun
31.9%
1m
Schedule
+14 months
| Sector | Information Technology |
| Responsible Entity | Department of Premier and Cabinet |
| Status | Completed |
| Original Completion | 10 May 2024 |
| Current Completion | 30 Jun 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.