Original Budget
$2m
Current Cost
$2m
Cost Overrun
10.3%
0m
Schedule
+14 months
| Sector | Information Technology |
| Responsible Entity | CenITex |
| Status | In Progress |
| Original Completion | 28 Jun 2024 |
| Current Completion | 31 Aug 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.