Report Card: [IT] Heavy Vehicle - Structural Assessment and Permit Syst… A
On Track
Original Budget
$6m
Current Cost
$6m
Cost Overrun
0%
Schedule
+6 months
| Sector | Transport |
| Responsible Entity | Department of Transport and Planning |
| Status | Completed |
| Original Completion | 20 Sep 2024 |
| Current Completion | 3 Apr 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.