[IT] Heavy Vehicle - Structural Assessment and Permit System (HV-SAPS)
Original TEI
$6.3m
Current TEI
$6.3m
Cost Overrun
$0.0m
0.0%
Schedule Overrun
6.4 months
Original: Sep 2024
→ Apr 2025
Cost Status
On Track
Time Status
Off Track
Description
The project delivers automation capability for Class 1 vehicle permit assessments, to enable automatic processing for 85% of permits to streamline approvals for the heavy vehicle industry, and reduce reliance on manual processing & contingent workers
Cost History (TEI over time)
Timeline Drift
No timeline snapshots recorded yet.