Original Budget
$7m
Current Cost
$12m
Cost Overrun
65.7%
5m
Schedule
+12 months
| Sector | Information Technology |
| Responsible Entity | Department of Energy, Environment and Climate Action |
| Status | Completed |
| Original Completion | 30 Jun 2024 |
| Current Completion | 30 Jun 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.