Original Budget
$7m
Current Cost
$12m
Cost Overrun
65.7%
5m
Schedule
+12 months
Sector Information Technology
Responsible Entity Department of Energy, Environment and Climate Action
Status Completed
Original Completion 30 Jun 2024
Current Completion 30 Jun 2025
Scope Changes 0 recorded
Cost RAG On Track
Time RAG Off Track
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.