Original Budget
$1m
Current Cost
$3m
Cost Overrun
191.6%
2m
Schedule
+38 months
| Sector | Information Technology |
| Responsible Entity | Melbourne Water |
| Status | In Progress |
| Original Completion | 10 Oct 2023 |
| Current Completion | 9 Dec 2026 |
| Scope Changes | 0 recorded |
| Cost RAG | Off Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.