Original TEI
$18.6m
Current TEI
$14.7m
Cost Overrun
$-4.0m
-21.2%
Schedule Overrun
19.0 months
Original: Nov 2025 → Jun 2027
Cost Status
On Track
Time Status
Off Track
Description

The program will upgrade network infrastructure and address the closure of data centres and the end-of-life of data centre assets through migrating workloads to Cloud. This program will deliver improved security and performance for our services.

Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.