Original Budget
$8m
Current Cost
$11m
Cost Overrun
41.5%
3m
Schedule
+10 months
| Sector | Health & Human Services |
| Responsible Entity | Austin Health |
| Status | Completed |
| Original Completion | 30 Jun 2024 |
| Current Completion | 30 Apr 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.