Original Budget
$8m
Current Cost
$11m
Cost Overrun
41.5%
3m
Schedule
+10 months
Sector Health & Human Services
Responsible Entity Austin Health
Status Completed
Original Completion 30 Jun 2024
Current Completion 30 Apr 2025
Scope Changes 0 recorded
Cost RAG On Track
Time RAG Off Track
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.