[IT] Victraffic Upgrade Project
Original TEI
$22.6m
Current TEI
$22.6m
Cost Overrun
$0.0m
0.0%
Schedule Overrun
24.0 months
Original: Jun 2024
→ Jun 2026
Cost Status
On Track
Time Status
Off Track
Description
Objective of this project is to support transport users and emergency response units to safely and confidently move around our road network during an emergency situation and improve road closure capture and uplift the user experience.
Cost History (TEI over time)
Timeline Drift
No timeline snapshots recorded yet.
Metadata