Original Budget
$139m
Current Cost
$136m
Cost Overrun
-1.7%
-2m
Schedule
+15 months
| Sector | Justice & Emergency |
| Responsible Entity | Country Fire Authority |
| Status | In Progress |
| Original Completion | 30 Jun 2024 |
| Current Completion | 30 Sep 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.