Report Card: [IT] Smarter Roads Program - Timetable Systems Uplift C
Significant Overruns
Original Budget
$5m
Current Cost
$7m
Cost Overrun
41.8%
2m
Schedule
+30 months
| Sector | Transport |
| Responsible Entity | Department of Transport and Planning |
| Status | In Progress |
| Original Completion | 31 Mar 2023 |
| Current Completion | 18 Sep 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | At Risk |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.