Original Budget
$17m
Current Cost
$18m
Cost Overrun
10.4%
2m
Schedule
+38 months
| Sector | Justice & Emergency |
| Responsible Entity | Fire Rescue Victoria |
| Status | In Progress |
| Original Completion | 30 Jun 2023 |
| Current Completion | 17 Aug 2026 |
| Scope Changes | 0 recorded |
| Cost RAG | At Risk |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.