Original Budget
$6m
Current Cost
$7m
Cost Overrun
15.0%
1m
Schedule
+20 months
| Sector | Justice & Emergency |
| Responsible Entity | Victorian Institute of Forensic Medicine |
| Status | In Progress |
| Original Completion | 31 Dec 2023 |
| Current Completion | 19 Aug 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Off Track |