Report Card: [IT] Strategic Relationship Management Tool Phase 1-2 C
Significant Overruns
Original Budget
$3m
Current Cost
$3m
Cost Overrun
0%
Schedule
+47 months
| Sector | Information Technology |
| Responsible Entity | Melbourne Water |
| Status | In Progress |
| Original Completion | 28 Jun 2022 |
| Current Completion | 28 May 2026 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.