Report Card: [IT] RTBA - Bond Management System Replacement C
Significant Overruns
Original Budget
$10m
Current Cost
$11m
Cost Overrun
15.1%
1m
Schedule
+36 months
| Sector | Information Technology |
| Responsible Entity | Department of Government Services |
| Status | In Progress |
| Original Completion | 30 Jun 2023 |
| Current Completion | 30 Jun 2026 |
| Scope Changes | 0 recorded |
| Cost RAG | At Risk |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.