Report Card: [IT] Better Technology Tools Enabling Responsibility (BTTER) F
Critical Failure
Original Budget
$19m
Current Cost
$54m
Cost Overrun
183.4%
35m
Schedule
+72 months
| Sector | Justice & Emergency |
| Responsible Entity | Department of Justice and Community Safety |
| Status | In Progress |
| Original Completion | 30 Jun 2023 |
| Current Completion | 30 Jun 2029 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.